Campus Disruptions

College of Education Building Elevator #2 Out of Service

Notification Date: July 18, 2017
Timeline: July 18, 2017 until further notice
Location: COE-ELEV2
Disruption: Elevator Out of Service
Disruption Plan: The issue has been identified and repairs are scheduled. 

Utility Infrastructure Upgrades Phase 3 

Notification Date: June 13, 2017
Timeline: June 16, 2017 - Until Further Notice
Location: Parking Lot B - Electrical Substation
Disruption: Parking Lot B
Disruption Plan:

Areas affected by Phase 3:

Phase 3 of the Utilities Infrastructure Project will focus on the replacement and relocation of the campus main electrical substation. The new campus electrical substation will be constructed on campus, adjacent to Parking Lot B. Some parking spaces in Lot B will be impacted during construction and restored when the project is complete in Fall 2018.

Vehicular Access will experience some impact in Lot B. Some parking spaces will be utilized by the contractor.

Pedestrian access will not be impacted.

Mobility Cart services will not be impacted.

Intermittent work at various locations across campus will take place throughout the project duration as crews verify existing utility locations.

Please reference the project map below.

The diagram highlights pedestrian paths, vehicular paths and construction fence placement for Phase 3. Further construction notices will be shared as the project progresses.

Please direct any questions to Al Salgado, Project Manager, Facilities Planning, Design and Construction, via email at asalgado@csusb.edu, or via phone at 909-537-5136.

Utility Infrastructure Campus Electrical Substation Phase 3

Utility Infrastructure Upgrades Phase 1 (Zone 3)

Notification Date: May 8, 2017
Timeline: April 3, 2017 - June 30, 2017
Location: Student Health Center and Counseling and Psychological Services Center
Disruption: ADA access
Disruption Plan:

Areas affected by Phase 1 (Zone 3) Construction

Beginning April 3rd through June 30th, construction will continue on a section of sidewalk south (Zone 2) of the Student Health Center, and will now expand east (Zone 3), with fencing continuing towards the housing construction area. Access to the Student Health Center from Student Union Lane will be available. Mobility cart route as well as ADA access to the Counseling and Psychological Services (CAPS) & Jack Brown Hall, will not be impacted.

Stair access to the CAPS main entrance will remain open.

ADA access to CAPS will be temporarily relocated to the north entrance to the building. The alternative route for ADA access is through the walkway east of the Student Health Center building and west of Jack Brown Hall to reach the north entrance to the building. 

Pedestrian access will remain open through the west sidewalk along Student Union Lane. 

Mobility Cart services provided by Services to Students with Disabilities will not be impacted. However, a new temporary pickup location, number 18B, will be provided at the temporary ADA north entrance to CAPS. Please refer to the attached map. 

Intermittent work at various locations across campus will continue to take place throughout the project duration as crews continue underground utility extensions.

Please reference the project map below. The diagram highlights pedestrian paths, Mobility cart route and temporary stop, and construction fence placement for Phase 1 (Zones 2 & 3). Further construction notices will be shared as the project progresses.

Please direct any questions to Al Salgado, Project Manager, Facilities Planning, Design and Construction, via email at asalgado@csusb.edu, or via phone at 909-537-5136.

Utility Infrastructure Health Center Phase 1 (zone3)

 

 

 

 

Student Housing & Dining Commons - Disruption Plan Phase 2.2

Utility Infrastructure Construction Phase 1 (Zone 4)

Notification Date:  May 10, 2017

Phase 1 (Zone 4) of the Utility Infrastructure Project underground work will begin on May 15, 2017.

Areas affected by Phase 1 (Zone 4)

Access for authorized service vehicles will be available through Education Lane, Student Union Lane and Coyote Court to service the following buildings: Pfau Library, Santos Manuel Student Union Events Center, Student Health Center, Jack Brown Hall, Physical Education. The Coussoulis Arena will be accessible throughLot G/Student Rec Center.

The North construction boundary fence will be relocated, encompassing a small portion of South Campus Circle in order to continue underground utility extensions.  Pedestrians coming from South Campus Circle and traveling to the East of Jack Brown Hall and are advised to travel through the Jack Brown Hall lobby and use the Northern walkways to travel to Physical Education, Recreation and Wellness and other Northerly buildings.

Mobility Cart Stop # 3 will remain at the North entrance doors to Jack Brown Hall. Pedestrians in need of mobility cart services are advised to travel through the Jack Brown Hall lobby and exit through the North doors to reach the temporary cart stop area.

Main vehicular roadway for Athletics & Events access will be impacted through Coyote Court.Alternate Route through Lot G adjacent to the Studen Rec Center.

Mobility Cart services provided by Services to Students with Disabilities will be rerouted around the construction area through pathways east of the Commons. No impact to mobility cart pickup locations is anticipated.  

Intermittent work at various locations across campus will take place throughout the project duration as crews verify existing utility locations.

Please reference the project map below. The diagram highlights pedestrian paths, vehicular paths and construction fence placement for Phase 1. Further construction notices will be shared as the project progresses.

Please direct any questions to Al Salgado, Project Manager, Facilities Planning, Design and Construction, via email at asalgado@csusb.edu, or via phone at 909-537-5136.

Utility Infrastructure Disruption Zone 4