The $1.4M project will upgrade all campus access layer network equipment that connects all campus buildings. CNI upgrade will cover all state buildings, while non-state buildings will be upgraded later this academic year and will be managed internally by ITS staff.  As approved by IT Governance, you will find the project migration schedule below.
 

Key Milestones

Dates Description Status
March 14 - April 23, 2019 Initiation & Planning Completed
April 3, 2019 Bill of Material (BOM) Approved Completed
April 11, 2019 Scope of Work (SOW) & Project Management Approach (PMA) Approval Completed
May 20, 2019 Begin Rotating Network Freeze (May 20 - Sep 11, 2019) In Progress
May 23, 2019 Project Schedule Approval Completed
May 28-31, 2019 Project Pilot Phase Completed
May 28 - August 27, 2019 Access Layer Installation In Progress
May 30 - September 11, 2019 Access Layer Migration In Progress
September 20-30, 2019 Final Testing and Acceptance  
September 25 - October 3, 2019 Project Closeout  



Migration Schedule

Users may experience brieft network interruptions during their scheduled migration window.
Impact: Minimal to Moderate
 

Migration Window Building/Floor
May 28-31, 2019
*Pilot Phase
FO - All - Completed
PL Addition - 1st, 3rd Floor - Completed
PL Tower - 2nd Floor
June 17-20, 2019 PL Addition - Basement, 1st, 3rd, 4th, 5th Floor - Completed
PL Tower - Basement, 3rd, 4th, 5th Floor - Completed
PL Wedge - 1st Floor - Completed
June 24-27, 2019 PL Tower - 1st Floor - Completed
SBS - All - Completed
June 28, 2019
*Friday Migration
PL Wedge - Basement, 1st, 2nd - Completed
July 1-3, 2019 CS - All - Completed
HA - All - Completed
PS - All - Completed
July 8-11, 2019 AF - All - Completed
AH - All - Completed
AS - All - Completed
BI - All - Completed
OB - All - Completed
VA - All - Completed
July 12, 2019
*Friday Migration
AD - All - Completed
ES - All - Completed
FM - All - Completed
UP - All - Completed
WH - All - Completed
July 15-18, 2019 AR - All - Completed
BK - All - Completed
CC - All - Completed
CH - All - Completed
IC1 - All - Completed
PA - All - Completed
SH - All - Completed
SS - All - Completed
July 23-25, 2019 UH - All - Completed
CE - All - Completed
July 31-August 1, 2019 CGI Trailer - All
IC2 - All
MC - All
PE - All
Soccer Field - All
TO - All
TC - All
TK - All
August 5-8, 2019 JB - All
August 12-15, 2019 HP - All
PDC IWC - All
PDC IWT - All
PDC RG - All
PDC HS - All
PDC UCR-A - All
PDC UCR-B - All
August 19 - September 11, 2019 Data Center