Common Network Initiative (CNI) Network Upgrade
As part of the systemwide Common Network Initiative (CNI), CSUSB will undergo a major network upgrade over the Summer 2019 quarter. The project began in March 2019 and is slated to complete by October 2019. Final testing will occur at the end of September 2019.
The $1.4M project will upgrade all campus access layer network equipment that connects all campus buildings. CNI upgrade will cover all state buildings, while non-state buildings will be upgraded later this academic year and will be managed internally by ITS staff. As approved by IT Governance, you will find the project migration schedule below.
Key Milestones
Dates | Description | Status |
---|---|---|
March 14 - April 23, 2019 | Initiation & Planning | Completed |
April 3, 2019 | Bill of Material (BOM) Approved | Completed |
April 11, 2019 | Scope of Work (SOW) & Project Management Approach (PMA) Approval | Completed |
May 20, 2019 | Begin Rotating Network Freeze (May 20 - Sep 11, 2019) | In Progress |
May 23, 2019 | Project Schedule Approval | Completed |
May 28-31, 2019 | Project Pilot Phase | Completed |
May 28 - August 27, 2019 | Access Layer Installation | In Progress |
May 30 - September 11, 2019 | Access Layer Migration | In Progress |
September 20-30, 2019 | Final Testing and Acceptance | |
September 25 - October 3, 2019 | Project Closeout |
Migration Schedule
Users may experience brieft network interruptions during their scheduled migration window.
Impact: Minimal to Moderate
Migration Window | Building/Floor |
---|---|
May 28-31, 2019 *Pilot Phase |
FO - All - Completed PL Addition - 1st, 3rd Floor - Completed PL Tower - 2nd Floor |
June 17-20, 2019 | PL Addition - Basement, 1st, 3rd, 4th, 5th Floor - Completed PL Tower - Basement, 3rd, 4th, 5th Floor - Completed PL Wedge - 1st Floor - Completed |
June 24-27, 2019 | PL Tower - 1st Floor - Completed SBS - All - Completed |
June 28, 2019 *Friday Migration |
PL Wedge - Basement, 1st, 2nd - Completed |
July 1-3, 2019 | CS - All - Completed HA - All - Completed PS - All - Completed |
July 8-11, 2019 | AF - All - Completed AH - All - Completed AS - All - Completed BI - All - Completed OB - All - Completed VA - All - Completed |
July 12, 2019 *Friday Migration |
AD - All - Completed ES - All - Completed FM - All - Completed UP - All - Completed WH - All - Completed |
July 15-18, 2019 | AR - All - Completed BK - All - Completed CC - All - Completed CH - All - Completed IC1 - All - Completed PA - All - Completed SH - All - Completed SS - All - Completed |
July 23-25, 2019 | UH - All - Completed CE - All - Completed |
July 31-August 1, 2019 | CGI Trailer - All IC2 - All MC - All PE - All Soccer Field - All TO - All TC - All TK - All |
August 5-8, 2019 | JB - All |
August 12-15, 2019 | HP - All PDC IWC - All PDC IWT - All PDC RG - All PDC HS - All PDC UCR-A - All PDC UCR-B - All |
August 19 - September 11, 2019 | Data Center |